We finally started the deck construction. When I said *we* of course I meant just Kitty, since she is the handy one between the two of us. Steve (the guy in the yellow shirt) is our contractor. He is very nice and professional.Day-1 involves just digging the holes. The frost-line for Kingston area is about 39in; the holes they dug were 4-feet deep. Our plan is to have a small top-deck of size 10'x7', a lower-deck of 16'x22', with a 3' feet of stairs between the decks.

Day-2 involved getting the city inspector to measure the depth of the holes. Once it was passed, the concrete was poured into the holes. On Day-3, once the concrete were set, joists, beams, and posts were installed.
Yes, Kitty did 1/2 of the actual work, following the instructions given by Steve. She is very sored, tanned, and proud.